Make to stock vs make to order: How to choose the right production strategy

8 min read
27. November 2026

Sales want to promise next-day delivery. Finance can see finished goods inventory growing. And production would rather run long batches to avoid too many changeovers.

In the middle of all that, someone has to decide which products you make to stock and which you only start once the customer has ordered. That is the choice between make to stock and make to order. And it does not have to be one choice for the whole factory.

This article gives you the two questions that frame the decision, an explanation of the decoupling point where the two strategies meet, and a worked example showing what the choice means for working capital and lead time.

What is the difference between make to stock and make to order?

With make to stock (MTS) you produce to a forecast before the customer has ordered. The product is ready when the order arrives. With make to order (MTO) production only starts once there is a confirmed order.

The difference lies in how you manage uncertainty. With make to stock you tie up capital in finished goods that may not sell. With make to order you do not need to produce the finished product to stock, but the customer has to wait, and you need the capacity to produce when the order arrives.

Make to stock has clear advantages: short delivery times, a more even load on production and the option of longer runs. The price is working capital tied up in finished goods and the risk of having built the wrong variants. Make to order keeps finished goods inventory low and lets you tailor the product to each customer. In return, delivery takes longer, and production has to keep up when orders arrive unevenly.

When should you use make to stock or make to order?

Revenue alone does not tell you whether an item should be made to stock or to order. Two questions tell you more. They are based on Jan Olhager's model for positioning the order penetration point (Olhager, 2003: "Strategic positioning of the order penetration point").

1. Can you make it in time once the order arrives?

Compare two times: the total time it takes to source materials and produce the item (P), and the delivery lead time the customer accepts (D). P covers the remaining lead time from the point where inventory is held to delivery. That can easily be the purchase of raw materials rather than production itself.

If P is shorter than D, you can in principle wait for the order, as long as production has the capacity to make it in time. If P is longer than D, you cannot rely entirely on make to order. Something has to be ready before the customer orders. The only question is what.

D is what the customer actually accepts, not what sales assume the customer wants. That figure is worth checking before you build inventory to keep a promise nobody asked for.

2. How predictable is demand?

Make to stock assumes you can forecast demand reasonably well. Olhager measures this with the coefficient of variation: the standard deviation of demand divided by the mean. It is the same figure used in an XYZ analysis. The lower the variability and the higher the volume, the easier an item is to build to stock. The more it fluctuates, the more expensive it is to keep it ready.

Customization belongs here too. If every order is unique, you cannot build the finished product in advance. But you may be able to hold the components that recur across orders.

Put the two questions together and you have a starting point for your MTS vs MTO strategy. A short P and volatile demand point towards make to order. A long P and stable demand point towards make to stock. A long P and volatile demand is the difficult combination. Here the decoupling point can be the answer, if your variants share components.

Make to stock or make to order: the decoupling point decides where you switch

You do not have to choose between pure make to stock and pure make to order. The decoupling point (the customer order decoupling point) is the stage in production where a product becomes tied to a specific customer order. Before that point you buy or produce based on expected demand. After it, you do so based on a confirmed customer order.

Move the point close to the finished product and you approach make to stock: fast delivery, more inventory, less flexibility. Move it back towards raw materials and you approach make to order. In between sits assemble to order, where you hold standard components or semi-finished goods and only assemble, paint or configure once the customer has ordered.

A good position meets two conditions. The time from the decoupling point to delivery must stay within the customer's lead time. And the items before the point should be shared by as many variants as possible, because when several variants draw on the same component, their demand fluctuations can partly cancel each other out. The effect is smaller if all variants rise and fall at the same time. Your bill of materials shows where variants share components.

Worked example: how much working capital do 60 variants tie up in inventory?

The example is constructed and every figure is an assumption, so you can follow the logic and check the maths.

A manufacturer makes steel control cabinets in three sizes. Each size comes in 20 configurations with different colours, door types and mounting plates, giving 60 variants in total. The customers are installers who accept a delivery lead time of 10 working days.

Step Working days
Steel sheet from the supplier 30
Bending and welding the cabinet 5
Powder coating and assembly 3
Packing and shipping 2
Total 40


If the manufacturer makes everything to order, P is 40 days against the customer's 10. That does not work. If it holds steel sheet in inventory, P is 10 days. That is exactly the customer's limit, so any queue in bending or welding becomes a late delivery.

Today the manufacturer solves this by building all 60 variants to stock. It holds an average of 4 units of each variant at a cost of €870 per unit:

60 × 4 × €870 = €208,800 in finished goods.

The alternative is to move the decoupling point to the unpainted cabinet. The manufacturer holds cabinets in the three sizes and does coating, assembly and shipping to order. P after the decoupling point is 3 + 2 = 5 working days, which leaves a five-day buffer within the customer's accepted lead time.

An unpainted cabinet costs €400. Because each size covers 20 variants, inventory can be pooled across variants. In the example we assume that 30 cabinets per size give the same availability as before. In practice, calculate the number from demand and replenishment lead time. On top of that come parts for the different configurations, set at €16,000:

3 × 30 × €400 + €16,000 = €52,000.

The difference is around €157,000. It comes from two things. Each unit in inventory is worth less before it is painted and assembled. And fewer units are needed because demand across 20 variants can be covered by a shared stock of cabinets.

The price is lead time. From finished goods inventory, the manufacturer could ship within a couple of days. Now it takes five. Coating can also become a bottleneck, as the three-day lead time depends on there being no backlog of orders.

So the manufacturer ends up with a mix. The five variants that sell the most and the most steadily, where some customers need next-day delivery, stay in finished goods inventory with 6 units each:

5 × 6 × €870 = €26,100.

In total, the hybrid ties up around €78,000 in cabinets, parts and finished goods, compared with €208,800 in finished goods before. That is €131,700 less. The cabinet inventory has not been reduced even though the five variants now sit in finished goods, and changes in raw materials and work in progress are not included. The result depends on the assumption about how many cabinets you need to hold. Work that out with your own demand data, for example with a safety stock calculation for each cabinet size.

What can change the MTO vs MTS decision?

The customer's lead time and demand variability give you the starting point. Four factors can shift it.

Suppliers. A supplier whose lead time swings between four and eight weeks makes P less predictable. You then need more buffer before the decoupling point, or you need to move the point closer to the finished product. You only see how unstable a supplier is when you measure supplier performance on actual lead times.

Minimum order quantities. If a supplier requires minimum order quantities larger than a single customer order can cover, you can end up with inventory even when you make to order. That inventory is caused by purchasing terms, and you deal with it in the negotiation, not by switching strategy.

Capacity and changeovers. If small batches mean frequent and expensive changeovers, longer runs to stock may pay off. On the other hand, long runs tie up working capital in products nobody has ordered yet. So work out what it costs to change the production pattern, and watch bottlenecks such as coating in the example.

Product life cycle. A new variant with no history is hard to build to stock. A variant on its way out can leave excess inventory that nobody buys. Demand shifts, so a decision that was right two years ago can be wrong today.

The two questions are easy to ask for one control cabinet. The hard part is answering them for thousands of item numbers, where demand and lead times keep changing.

With Inact's inventory optimisation you can categorise items by importance and demand, plan from demand forecasts and adjust service levels, safety stock and reordering to each item's role. That gives you a basis for seeing which items are worth holding in inventory, and where you tie up working capital without improving delivery performance.

Frequently asked questions about make to stock and make to order

What is the difference between make to stock and make to order?

Make to stock produces to a forecast, so the product is ready when the customer orders. Make to order only starts production once an order has been received. The first gives short delivery times and more inventory. The second gives less finished goods inventory and a longer wait for the customer.

What is assemble to order?

Assemble to order is a hybrid where you hold components or semi-finished goods in inventory and only assemble the finished product once the customer has ordered. It gives shorter delivery times than pure make to order and less finished goods inventory than make to stock, provided the variants share components.

What is a decoupling point in production?

The decoupling point is the stage in production where a product becomes tied to a specific customer order. Before that point you buy or produce based on expected demand. After it, you do so based on a confirmed customer order. Its position determines both how much inventory you hold and how quickly you can deliver.

When should you choose make to stock over make to order?

Make to stock is a natural starting point when demand is fairly stable and the customer wants the product faster than you can source materials and produce it. Make to order fits better when the customer can wait, demand is hard to forecast, or the product has to be tailored to the order. You can also combine the two by holding shared components and finishing the product to order.

What are the disadvantages of make to stock?

You tie up working capital in finished goods before they are sold, and if the forecast is wrong you end up with the wrong variants. The risk grows with the number of variants and with how much demand fluctuates.